Underground flood tunnels could cost $30 billion, Harris County Flood Control District says
-
Maintenance man killed as he stepped in between gunman, coworker: HPD Police are searching for Cardarius Jamar Woodard, charged in the death of maintenance man David Walters at an apartment in the Montrose area.
ABC 13 Houston
-
'Something's not right': Wife losing hope after husband goes missing John Davis' truck was found empty four months after he was considered missing by Mount Vernon police, who say the case is not their responsibility, but HPD's.
ABC 13 Houston
-
Afghan refugees helping others in Houston 1 year after Taliban takeover Marking a year since the U.S. pulled out of Afghanistan, the thousands of refugees in Houston are still getting acclimated to their new home, especially in spite of language barrier issues. But that's not keeping some of them from helping each other.
ABC 13 Houston
Findings from an ongoing Harris County Flood Control District feasibility study estimate a $30 billion price tag for a potential countywide stormwater conveyance tunnel system.
The video above is from a previous story.
Funded by a $2.5 million grant from the U.S. Department of Housing and Urban Development, Phase 2 of the district's feasibility study identified eight tunnel alignments that would mostly follow existing channels.
SEE RELATED STORY: Harris County Flood Control District could have biggest spending year yet in 2022
HCFCD officials presented Phase 2 of the study at a virtual community engagement meeting June 16.
The study determined that 11 of the county's 23 major watersheds would receive the greatest benefit from a tunnel system, taking into account factors such as population density and concentrated areas known as "damage centers" where homes and businesses repeatedly flood.
The next phase of the study is set to begin in early 2023 and could last about three years, according to Scott Elmer, assistant director of operations for HCFCD. Phase 3 is backed by $20 million in bond funding from HCFCD's $2.5 billion bond approved by voters in 2018, and it will focus on tightening up the engineering details and investigating sources of funding for the project.
"We will leave no stone unturned when it comes to funding," Elmer said. "We'll investigate funding at all levels. I'm not going to be able to say today whether this is something [the Federal Emergency Management Agency would] say is right up [its] alley, but it's something we're looking at in Phase 3."
With the size and scale of the tunnel system, county funding would likely be needed to supplement state and federal funding.
Upside of underground tunnels
According to Elmer, one big advantage of a tunnel system is the reduced land acquisition when compared to traditional methods of flood management, such as stormwater basins or buyouts. In one unspecified tunnel alignment, Elmer said 27 acres of land would be needed for a tunnel, over 90 times less than the 2,483 acres of land needed to build traditional stormwater infrastructure.
Running 100 feet underground, the 35- to 40-foot diameter concrete tunnels would be built under existing channels and use public rights of way as much as possible, according to Elmer.
He added that over a service life of 100 years, 80,000-120,000 cumulative instances of flooding could be avoided. This number includes structures that flood infrequently to ones located in low-performing watersheds with more frequent flooding.
The public comment period before Phase 3 closes on Sept. 30. The flood control district posts updates on its website.
This content was provided by our partners at Community Impact Newspaper.
More From ABC 13 Houston
-
Conroe ISD bus driver dropped off 3rd grader and 5-year-old twins at wrong stops 4 days apart
ABC 13 Houston
-
Student accused of setting fire to University of Houston dorm building, damaging 4 floors
ABC 13 Houston
-
Apartment worker in The Woodlands accused of breaking into unit and climbing into girl's bed naked
ABC 13 Houston